Construction
Construction Phases
Construction of the I-5 Rose Quarter Improvement Project will begin in summer 2025 with Phase 1A construction, followed in 2027 by Phase 1 construction. Click on the tabs below to learn more about each phase.

Phase 1A Construction (Summer 2025)
- Stormwater improvements near the intersection of I-5 and I-405
- Bridge work near the intersection of I-5 and I-84
- Signage for highway cover safety and construction

Phase 1 Construction (2027)
- Build southern portion of the highway cover (30% of cover length) and multimodal improvements
- Complete southbound auxiliary lane and shoulder from I-405 to the Morrison Bridge exit
- Extend the northbound auxiliary lane and shoulder under the highway cover
- Install signage for highway cover safety and construction
- Widen Holladay/Hassalo bridge

Future Project Phases
Construction of Phase 1A and Phase 1 components will support future construction phases to complete the project in full. ODOT and our partners – City of Portland, Metro, Albina Vision Trust and the Portland Trail Blazers – are committed to completing the project in its entirety. Future project phases are currently unfunded.
Numbers on the map correspond to descriptions on the right.
Phase 1 Construction (2027-2031)
Components:
- Build southern portion of the highway cover (30% of cover length) and multimodal improvements
- Complete southbound auxiliary lane and shoulder from I-405 to the Morrison Bridge exit
- Extend the northbound auxiliary lane and shoulder under the highway cover
- Install signage for highway cover safety and construction
- Widen Holladay/Hassalo bridge
Benefits:
- Provides needed freeway safety improvements
- Creates community development opportunities on and off the highway cover following Phase I
- Complements the City of Portland’s Reconnecting Communities and Neighborhoods grant project focused on Broadway and Weidler
- Uses an efficient approach to construction that minimizes cost and keeps the traveling public moving during construction
- Facilitates the relocation of the southbound I-5 off-ramp in a future construction phase
How We Are Building It
Construction Manager/General Contractor
A Construction Manager/General Contractor (CM/GC) is a project delivery method where project contracts are released in two phases: first design and later construction. The project owner hires a contractor to provide feedback during the design phase, before construction begins.
A Mini CM/GC method follows the same phasing but is geared to smaller companies. Mini CM/GCs join the project during the design phase and complete work on smaller work contracts within the larger project.


Hamilton/Sundt, a Joint Venture (HSJV), in association with Raimore Construction (one of the largest Black-owned contractors in Oregon), is the project’s Construction Manager/General Contractor (CM/GC).
In 2022, ODOT selected three Mini CM/GCs (all Disadvantaged Business Enterprises) to complete early work. The Project team, including the project’s CM/GC, also published the Diversity and Subcontracting Plan. To learn more about the project’s commitment to workforce development, visit our Workforce Opportunities page.