Construction

Construction Phases

Construction of the I-5 Rose Quarter Improvement Project will begin in summer 2025 with Phase 1A construction, followed in 2027 by Phase 1 construction. Click on the tabs below to learn more about each phase. 

Phase 1A Construction (Summer 2025)

  1. Stormwater improvements near the intersection of I-5 and I-405
  2. Bridge work near the intersection of I-5 and I-84
  3. Signage for highway cover safety and construction

Learn More  

Numbers on the map correspond to descriptions on the right. 

Phase 1 Construction (2027-2031) 

Components: 

  1. Build southern portion of the highway cover (30% of cover length) and multimodal improvements
  2. Complete southbound auxiliary lane and shoulder from I-405 to the Morrison Bridge exit
  3. Extend the northbound auxiliary lane and shoulder under the highway cover
  4. Install signage for highway cover safety and construction
  5. Widen Holladay/Hassalo bridge

Benefits:

  • Provides needed freeway safety improvements
  • Creates community development opportunities on and off the highway cover following Phase I
  • Complements the City of Portland’s Reconnecting Communities and Neighborhoods grant project focused on Broadway and Weidler
  • Uses an efficient approach to construction that minimizes cost and keeps the traveling public moving during construction
  • Facilitates the relocation of the southbound I-5 off-ramp in a future construction phase

How We Are Building It

Construction Manager/General Contractor

A Construction Manager/General Contractor (CM/GC) is a project delivery method where project contracts are released in two phases: first design and later construction. The project owner hires a contractor to provide feedback during the design phase, before construction begins.

A Mini CM/GC method follows the same phasing but is geared to smaller companies. Mini CM/GCs join the project during the design phase and complete work on smaller work contracts within the larger project.

 

Hamilton Sundt A Joint Venture in Association with Raimore logo

Hamilton/Sundt, a Joint Venture (HSJV), in association with Raimore Construction (one of the largest Black-owned contractors in Oregon), is the project’s Construction Manager/General Contractor (CM/GC).

In 2022, ODOT selected three Mini CM/GCs (all Disadvantaged Business Enterprises) to complete early work. The Project team, including the project’s CM/GC, also published the Diversity and Subcontracting Plan. To learn more about the project’s commitment to workforce development, visit our Workforce Opportunities page.