I-5 Rose Quarter Update: Seismic retrofitting advances; expect traffic impacts

Over the past two months, crews have been working hard to make I-5 stronger and safer in the event of an earthquake. 

Crews work on removing lead paint on I-5 bridge supporting structures.

Crews work on removing lead paint on I-5 bridge supporting structures.

To make these bridges resilient to earthquakes, they need to be reinforced to withstand both forward-backward movement and side-to-side movement. These critical upgrades will ensure that I-5 will remain functional in case of a seismic event.

To address forward-backward movement, crews are installing cables stretching between the beams under the roadway and supporting cement columns. These cables will tie the beams to the columns to make sure that the beams will not shift during an earthquake and fall off the column.

The team must first scan the cement to identify where it is safe to drill into the concrete to reduce chances of damage to the rebar inside. Then they drill into the concrete to anchor the bolts for the cable restrainer that hold the beams in place.

The cables will then be attached to the beams supporting the I-5 bridge deck using bolts. For workers to safely install the bolts on I-5 supporting beams, lead paint on the beams must first be removed.

To address side-to-side movement, the project will be replacing the existing cross bracing under I-5. The cross bracing helps to prevent the beams from tipping sideways during an earthquake event. The new cross bracing will meet updated earthquake standards.

Over the coming months, additional closures will occur on NE Oregon St and NE Lloyd Blvd for crews to install cables and cross bracing under I-5. 

Crews remove lead paint on beams under I-5 to prepare for installation of bolts.

Crews remove lead paint on beams under I-5 to prepare for installation of bolts. 

Crews drill into the concrete supporting columns to install cable bolts. Lines drawn onto the cement indicate locations of rebar inside the cement.

Crews drill into the concrete supporting columns to install cable bolts. Lines drawn onto the cement indicate locations of rebar inside the cement.  

Image shows cross bracing in between two I-5 supporting beams.

Image shows cross bracing in between two I-5 supporting beams.

Upcoming Traffic Impacts

Construction on the I-5 Rose Quarter project is picking up the pace in 2026 with multiple I-5 and local street closures starting in January.

In December 2025, there will be an overnight lane closure on I-5 SB between the I-84 exit ramp and the Morrison Bridge/OMSI exit to prepare for installation of a new sign bridge over I-5. This will occur on either the night of Friday Dec. 19, Monday Dec. 22, or Tuesday Dec. 23 depending on weather conditions.

In January 2026, additional I-5 and local street closures are planned:

  • Overnight lane closures on I-5 for barrier strengthening and prep work on I-5. 
  • Closures of the I-84 Exit to Moda and the Oregon Convention Center (connecting to NE Holladay St) for construction of foundations for the new sign bridge. 
  • Additional local street closures on N Interstate Ave and NE Lloyd Blvd for sign bridge and seismic strengthening work. 

Sign up for text alerts and visit our Construction Travel Impacts page to stay up-to-date with the latest news on traffic impacts and active closures.

Map communicating eventual Phase 1A lane, ramp, and road closures including Interstate Avenue, NE Oregon St, NE Lloyd Blvd and I-84 Westbound exit ramp. Also included is open bicycle and pedestrian access along Interstate Avenue, NE Oregon St and NE Lloyd Blvd.

Translation/Interpretation Accommodations

For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

如果您想瞭解這個項目翻譯成 繁體中文 的相關資訊,請致電 503-731-4128.

如果您想了解这个项目翻译成 简体中文 的相关信息,请致电 503-731-4128.

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128.

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.

For 24/7 road conditions and traffic alerts visit tripcheck.com or call 5-1-1.

Visit the Portland Area Construction Information website for more information about projects in construction.