Construction Progresses on Stormwater Facilities
to Improve Willamette River Water Quality

Image shows construction of a new stormwater treatment facility near the junction of I-5 and I-405.

Crews complete excavation for new stormwater treatment facility

The I-5 Rose Quarter Project is doing its part to keep our rivers clean. 

Crews are building two new stormwater facilities near the junction of I-5 and I-405 to improve Willamette River water quality by gathering and treating storm runoff from I-5, I-405, and surrounding areas. 

A new stormwater treatment facility is under construction near N Mississippi Ave. This facility will capture runoff in one location where it can be filtered through layers of plants and mulch, preventing pollutants from entering our waterways and rivers. Crews have completed excavation and are working on laying underground piping this month.

Crews will also begin work on a new underground stormwater vault in the coming weeks, located underneath the I-405 and I-5 highway ramps. The vault will capture stormwater runoff and release it slowly, allowing time for sediment, which is known to increase temperatures when suspended in water, to settle before the water is discharged. 

Work continues on I-5 safety upgrades;
expect intermittent overnight lane closures

Graphic showing the closure of I-5 northbound and southbound left lanes between the Oregon Convention Center and Burnside Bridge

 

Over the past two months, crews have been working along I-5 to complete maintenance and upgrades between the Moda Center and Burnside Bridge. 

In February and March, expect intermittent overnight lane closures on I-5 northbound and southbound as crews work to install new, taller barriers that meet current traffic safety standards along the outside of the highway and in the median. Closures will take place as weather permits.

Construction on this section of I-5 is expected to continue off and on until fall 2026. Sign up for text alerts and visit our Construction Travel Impacts page to stay up-to-date with the latest news on traffic impacts and active closures.

I-5 Rose Quarter Project selected for inaugural technical assistance award

The Rose Quarter Project learned in early January that it was selected to be in the initial cohort of projects supported by AmericaFWD’s Project Delivery Accelerator Lab (Lab), a national program focused on helping complex infrastructure projects move faster and more effectively from planning to construction. 

The Lab’s technical assistance and rapid response support will strengthen the project’s capacity to address delivery challenges, collaborate with partners, and advance the Rose Quarter Project to improve safety, mobility, and economic opportunity throughout the region. 

Read the official release from AmericaFWD here.

AmericaFWD Logo

Joint meeting of Rose Quarter advisors scheduled for Feb. 11

The public is invited to attend an upcoming meeting for the I-5 Rose Quarter Improvement Project:

On Wednesday, February 11, the Historic Albina Advisory Board (HAAB) and Community Oversight Advisory Committee (COAC) will meet from 5:00–7:00 p.m. The meeting will be in-person at Albina Library, located at 205 NE Russell St, Portland, OR 97212. The meeting will also be available via YouTube livestream.

Anyone can observe the meeting and share comments via email, phone or in person. Please visit the project’s events and meetings page for more information on how to view the meeting and share a comment.

All project committee meetings are open to the public. If you require accommodations or would like more information, please contact the project team at 503-470-3127 at least 48 hours in advance of the meeting. 

Translation/Interpretation Accommodations

For ADA Title II or Civil Rights Title VI accommodations, translation/interpretation services or for additional information call 503-731-4128, TTY (800) 735-2900 or use the statewide Oregon Relay Service: 7-1-1.

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128.

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128.

如果您想瞭解這個項目翻譯成 繁體中文 的相關資訊,請致電 503-731-4128.

如果您想了解这个项目翻译成 简体中文 的相关信息,请致电 503-731-4128.

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128.

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.

For 24/7 road conditions and traffic alerts visit tripcheck.com or call 5-1-1.

Visit the Portland Area Construction Information website for more information about projects in construction.